Isle of Man Railways does not have a target completion date for the restoration of one its vintage locomotives - and says it cannot give an update on progress.
No.16 Mannin had languished, in virtually original condition, in Port Erin railway museum for years.
But in 2019, the then director of public transport Ian Longworth announced a plan to restore the 1923-built engine to full working order in time for the line’s 150th anniversary in 2023.
That ambition was never met.
In 2020, Mannin’s boiler was shipped to the Severn Valley Railway in Shropshire for major repairs. It remains there to this day together with the loco’s chassis, side tanks and cab. Other parts are stored at the railway workshops in Douglas.
Responding to a Freedom of Information request seeking an update on Mannin’s progress, the Department of Infrastructure said it does not hold a current progress/status report or a current target or estimated date for completion of the restoration works and the loco’s return to service.
It said it could not disclose commercially sensitive financial information.
But it has released emails that reveal the project has ‘crept and changed’ since Mannin arrived at the SVR.
The head of steam engineering at the SVR said to Isle of Man Railways in September last year: ‘Currently I'm unsure of what we have committed to regarding further work on No.16.
‘But I need to see where it's at as the project has obviously crept and changed since its arrival here for trial fitting of a boiler in the frames.’
He said the boiler is nearly complete and ‘as predicted and suspected some time ago this will be ready long before the rest of the locomotive’.
The DoI has been approached for a comment.
The published emails include a series of invoices raised against purchase orders. They do not include the sums requested and paid.
In 2022 SVR quoted £14,000 for a new steel firebox, replacing the original copper one, plus £19,000 for associated formers and pressings.
IoM Railways had wanted as much of the original boiler saved as practical. In the event only 15% of the boiler shell could be salvaged.
An email from 2024 showed the charge per boiler including materials and steam test had increased from just over £93,000 in 2019 to more than £114,000.
In January this year, a twist in the rear end of the frames was discovered.
IoM Railways raised another purchase order in September last year for getting the boiler fitted, correcting the frames and turning Mannin into a rolling chassis.
It raised another purchase order the following month for a replacement smokebox.
The last invoice included with the FoI response dates from November last year.
Shortly after the boiler arrived at the SVR it was stripped and brass tubes, weighing 1,020kg removed.
An email to IoM Railways in January 2021 said a valuation for the brass had been sought from two local scrap dealers.
It asked: ‘What do you want to do about this “scrap”? Ideally we’d like to get rid of them sooner rather than later as they’re a bit in the way - and obviously we don’t want to leave them outside!’