Energy firm Ørsted says it remains confident that its proposed Mooir Vannin offshore windfarm can generate its first electricity by the mid-2030s.
It has issued a response after it emerged that official records show that Mooir Vannin has no confirmed connection date to the UK grid.
The National Energy System Operator’s Transmission Entry Capacity (TEC) Register gives only an indicative date of September 30, 2037.
Businessman Peter Taylor, an island-based chairman of an energy storage company, has written to the Chief Minister and every Tynwald member after checking the official grid records.
He said what they show is a serious concern.
‘A wind farm cannot generate a single unit of electricity until it is connected,’ he said.
‘No connection means no generation. And no generation before 2037 means no generation income and no production-based seabed rent to the Isle of Man Government before 2037 at the earliest.’
He claimed this undermines the project's viability.
Mr Taylor said: ‘To win a UK government Contract for Difference - the subsidy these projects depend on - a scheme has to be genuinely deliverable within the auction's timescale.
‘No bank and no investor commits billions to build a 1,400 MW wind farm without a confirmed grid connection and a firm route to revenue.’
The Council of Ministers is due to receive a report from the independent examining body on December 1, with its recommendation on whether or not Mooir Vannin should be given the go-ahead.
An Ørsted spokesperson said: ‘We remain confident that Mooir Vannin can achieve its ambition of generating electricity in the mid-2030s. The date within the NESO TEC Register is indicative and should not be confused with a confirmed final or “earliest” connection date.
‘We are engaging directly with NESO and NGET (National Grid Energy Transmission) to progress our connection arrangements.
‘There remains an opportunity to secure an earlier connection through the Gate 2 process and Mooir Vannin has all the required information in place to submit an application at the next window.
‘Grid connections are an evolving area of the UK energy system with significant work underway to accommodate new generation. It is not unusual for a firm grid connection to be secured after planning consent is granted.’
But Mr Taylor said from his home in Maughold: ‘Ørsted don't dispute a single fact I raised.
‘They confirm they do not hold a firm (Gate 2) grid connection. The only date on any official record is still September 30 2037.
‘And their own target has slipped from the 2031–2033 their technical director gave publicly to "the mid-2030s" — which they now call an "ambition".
‘But "indicative" cuts both ways — the date can move later as easily as earlier. Ørsted do not claim to hold any earlier date.’
Mr Taylor said Ørsted’s comment about there being an opportunity to secure an earlier connection was a ‘key admission’.
He said: ‘They are still waiting to apply. And applying is not the same as getting an earlier date. There are already other large wind farms ahead in the queue.’