A £1.4 million water project in West Baldwin has been delayed by six weeks, Manx Utilities has confirmed.
The project, which is aimed at improving the resilience of the island's raw water supply from West Baldwin Reservoir, involves installing a new siphon system to help maintain the movement of water through the reservoir infrastructure.
Providing an update on progress, Manx Utilities said work in the river has now been completed, while construction of new chambers is progressing.
An 83-metre section of pipe, which will form a key part of the scheme, has also been welded and is awaiting installation.
The delay follows the discovery of unmapped underground services and a high water table, which presented additional construction challenges.
Despite the delays, Manx Utilities has said the project remains within its original budget, with completion now expected by the end of December.
As a result of the delays, West Baldwin Road has reopened with traffic lights operating until December 19, while East Baldwin Road, also known as Ballamodha Road, will remain closed until the same date.
A spokesperson from Manx Utilities commented: ‘The project will improve emergency response capability and provide a more resilient raw water supply from West Baldwin Reservoir, while enabling ageing infrastructure to be replaced and refurbished.
‘We recognise the disruption caused by the extended works and thank residents, road users and the local community for their continued patience and cooperation.’
The scheme forms part of the utility's ongoing work to maintain and improve the island's water infrastructure and ensure the continued reliability of its supply network.