The Steam Packet has pushed back the expected return of its £78m flagship Manxman until December 11 after further problems emerged during repair work on the vessel's propulsion system.
The company confirmed today (Monday) that the ferry, which had been expected to return to service by the end of November, will remain out of action for at least another fortnight.
The latest delay follows the discovery of an issue with the locking arrangement for the vessel's replacement bearings during installation work last week.
The Steam Packet said the existing arrangement no longer met the 'fine tolerances' required to secure the bearings correctly, meaning new tapered locking wedges must now be manufactured.
Once the parts have been delivered, the remaining work will include reassembly, regulatory inspection and sea trials.
The company stressed that December 11 was an expected return date, subject to the delivery of the outstanding components and completion of the necessary work.
It will confirm the date once the parts have arrived and said it would provide an immediate update if there were any further changes.
Passengers whose bookings are affected will be contacted directly by the company's reservations team from today, with customers being approached in travel-date order and assisted with alternative arrangements.
Managing director Brian Thomson apologised to those affected by the latest extension.
He said: ‘Firstly, I would like to apologise to all affected customers for the inconvenience caused by this further delay.
‘Although this is not the outcome we had hoped to announce today, it's important that we complete this work to the highest standard before Manxman returns to service.’
He added that the company understood the extension would be frustrating for passengers and that its teams were focused on completing the work safely and efficiently.
The cause of the original wear to the vessel's propulsion system is also being investigated independently by maritime classification society Lloyd's Register.
Mr Thomson said the company would provide an update on its findings once that investigation had been completed.
The latest setback comes after weeks of work on the vessel, which has been out of service since October while undergoing repairs and dry-docking in Birkenhead.
Specialist teams have been working on the propulsion system, with replacement bearings manufactured by SKF following measurements and machining work involving specialists from MarineShaft.
The work has also involved modifications to the vessel's A-frame and P-frame support structures, which house the bearing carriers.
The repairs and dry-docking have previously been estimated to cost about £5m.
The Steam Packet said it would continue publishing weekly updates until Manxman returns to service, or sooner if there is significant news.
Passengers can find the latest information at steam-packet.com/manxman-update.


-(2).jpeg?trim=0,0,0,0&width=752&height=501&crop=752:501)




Comments
We've recently changed our login process. If you have an account for commenting, you will need to re-register on the login window.
This article has no comments yet. Be the first to leave a comment.